| Construction History |
 |
- 1902 Two-story, four room frame structure built for $2,000
- 1912 Three-story brick structure on Maple Street completed
- 1922 Two-story building on Maple Street was built for $22,000
- 1935 Three story building on Maple Street demolished
- 1939 New facility on Maple Street completed by WPA, 39,875 s.f. for $95,000
- 1963 Bond issue of $220,000 passed to build Z. T. Acker Elementary
- 1964 Z. T. Acker Elementary completed, 38,217 s.f.
- 1966 Classrooms added to Z. T. Acker Elementary
- 1973 Playroom addition to Z. T. Acker Elementary
- 1973 Bond issue of $1,210,000 passed and new high school was built (now Staley), 69,000 s.f.
- 1981 Z. T. Acker Gym expansion 44,211 s.f.
- 1986 I. S. Rogers Elementary completed, 48,816 s.f.
- 1986 Memorial Stadium Complete next to high school
- 1987 Auditeria/Fine Arts addition to Frisco High, 23,340 s. f.
- 1991 I. S. Rogers Elementary Classroom addition, 15,080 s.f.
- 1994 Z. T. Acker Elementary remodeled
- 1995 Claude Curtsinger Elementary completed, 52,868 s.f.
- 1996 Additions to Claude Curtsinger Elementary, 10,000 s. f.
- 1996 Frisco High School on Parkwood completed, 124,771 s. f
- 1996 Renovations/Additions to old high school, becoming Benton A. Staley Middle
- 1997 Renovations to two-story building on Maple Street, becoming Administration Building
- 1997 Noel A. Smith Elementary completed, 62,350 s.f.
- 1997 Renovations and additions to Agriculture Science Project Barn
- 1997 Frisco High School addition - Indoor Facility 32,918 s.f.
- 1998 Frisco High School addition, 55,311 s. f.
- 1999 Naoma & M. Allen Anderson Elementary completed, 63,069 s. f.
- 1999 J. W. & Ruth Christie Elementary completed, 63,069 s. f.
- 2000 Adelle R. Clark Middle School completed, 132,200 s. f.
- 2000 Shawnee Trail Elementary completed, 63,943 s. f.
- 2000 Maple Street Complex and Student Opportunity Center
rennovated
- 2001 Acker Special Programs Center renovated
- 2001 Ruth Borchardt Elementary completed, 72,000 s. f.
- 2001 Ida Lee Bright Elementary completed, 68,000 s. f.
- 2001 Wilma Fisher Elementary completed, 68,000 s. f.
- 2001 Frisco Memorial Stadium Press Box and Turf
- 2001 Frisco High School Phase III addition 78,890 s.f.
- 2002 Bessie Ely Gunstream Elementary completed, 71,555 s. f.
- 2002 Pioneer Heritage Middle School completed, 137,245 s. f.
- 2002 Izetta Sparks Elementary completed, 71,555 s. f.
- 2002 Otis Spears Elementary completed, 71,555 s f.
- 2002 Cal & Walt Wester Middle School completed, 137,245 s.f.
- 2003 Centennial High School completed (All Buildings) 333,212 s.f.
- 2003 Jessie Marie Riddle Elementary completed 74,824 s.f.
- 2003 Mary M. Boals Elementary completed 74,824 s.f.
- 2003 Six Classroom additions to Curtsinger, Fisher, Anderson and Smith ~8,000 s.f. ea.
- 2003 FISD Natatorium 38,871 s.f.
- 2004 Service Center Phase I 24,377 s.f.
Phase II 18,866 s.f.
- 2004 Bert and Eloise Isbell Elementary 76,816 s.f.
- 2004 Bennett and Alma Griffin Middle 138,651 s.f.
- 2004 Six classroom additions to Bright, Christie and Shawnee Trail ~7500 s.f. ea
- 2004 Memorial Fieldhouse and Athletic Offices renovation 3,600 s.f.
- 2005 FISD Administrative Annex 20,740 s.f.
- 2005 Calvin Bledsoe Elementary 7,6816 s.f.
- 2005 Dr. Erwin G. and Elisabeth Pink Elementary 75,904 s.f.t
- 2005 Lucille Rogers Ashley Elementary 75,904 s.f.
- 2005 Sam and Ann Roach Middle 138,651 s.f.
- 2005 Pizza Hut Park - Dr. Erwin G. Pink Field
- 2006 Wakeland HS (All Buildings) 338,806 s.f.
- 2006 Weldon F. Corbell Elementary 75,904 s.f.
- 2006 Portia Ross Taylor Elementary 75,904 s.f.
- 2006 Pat and Catherine Fowler Middle 138,651 s.f.
- 2006 Isabel Pierce Sem Elementary 75,904 s.f.
- 2006 Dr. J.M. Ogle Elementary 75,904 s.f.
- 2007 Reba Cobb Carroll Elementary 75,902 s.f.
- 2007 Charlie and Charlotte Mooneyham Elementary 75,902 s.f.
- 2007 Robertson Elementary 75,902 s.f.
- 2007 Liberty High 340,000 s.f.
- 2008 Edris Childres Elliott Elementary 75,902 s.f..
- 2008 Polly Tadlock Elementary 77,184 s.f.
- 2008 Richard L. Scoggins Middle 142,108 s.f.
- 2008 Sue Wilson Stafford Middle 142,108 s.f.
- 2008 Sam Carter Service Center (47,884 s.f.
- 2008 Transportation - West 39,126 s.f.
- 2008 Career & Technology Education Center - 131,096 s.f.
- 2009 William H. & Abbie Allen Elementary 83,960 s.f.
- 2009 Early Childhood School 101,784 s.f.
- 2009 Heritage High School 350,535 s.f.
- 2009 Service Center Phase III 7,980 s.f.
- 2010 Cobb Middle 143,159 s.f.
- 2010 Hunt Middle 143,159 s.f..
- 2010 Maus Middle 143,159 s.f..
- 2010 Purefoy Elementary 79,844 s.f.
- 2010 Sonntag Elementary 76,952 s.f.
- 2010 Lone Star High 345,455 s.f.
|
| |
| |
|